AusIMM conference paper
Maximising asset value through optimal block by block decisions on marginal material
Cut-off grades average economics across whole zones, but two blocks of the same grade can be worth very different amounts depending on what they cost to reach, when spare capacity exists, and what higher-value ore they delay. This paper moves that economic logic into the schedule, so each underground block is kept or left based on its value in context.
In the case study, block-by-block valuation lifted NPV from $288M to as much as $335M, a 17% improvement over the conventional approach.